RPZ FAQs: Notification


When do I notify the installation or relocation of an RPZ valve?

Details of the proposed work/installation shall be sent to the relevant water undertaker no less than 10 working days before work is due to start. Installing or using RPZ valves without the required consent could result in enforcement action being taken by the water undertaker.

Please note that failure to provide the minimum level of information required may delay consent. Contact the local water undertaker for further information.

 


We use cookies to give you the best possible experience with Water Regs UK. Some are essential to provide website functions and ensure the website is secure. We also use cookies to help us understand how people use the site and to make improvements. Click "Accept All" to enable recommended settings or click "Manage cookies" to adjust your settings. For more details, see our Cookie Policy.